|     PJ - 273CLIENT: STATE OF KUWAIT - MINISTRY OF PUBLIC WORKS  
 PROJECT NAME : CONSTRUCTION AND MAINTENANCE OF ROADS, BRIDGES, STORM-WATER DRAINAGE, SEWER AND OTHER SERVICES FOR THE FIRST RING ROAD - DASMAN, ABDULLAH AL AHMAD STREET.CONSULTANT: PARSONS BRINCKERHOFF INTERNATIONAL INC. IN ASSOCIATION WITH GULF CONSULT
 MAIN CONTRACTOR : M.A AL KHARAFI & SONS
 SUB-CONTRACTOR : KUWAIT BRUCKNER CONSTRUCTION CONTRACTIN
 
 | 
              
    |     PJ - 284CLIENT: YUSUF AHMED ALGHANIM & SONS CO.  
 PROJECT NAME: SHORING, DEWATERING & EXCAVATION WORKS FOR NEW FORD SHOWROOM CONSULTANT: MIMAR DR. M. Y. AL-AWADHI CONSULTAN
 | 
              
    |     PJ - 286CLIENT: STATE OF KUWAIT - MINISTRY OF PUBLIC WORKS  
 PROJECT NAME: CONSTRUCTION, COMPLETION & MAINTENANCE OF AL GHOUSE ROAD FROM 5TH TO 6TH RING ROAD CONSULTANT: EGIS INTERNATIONAL IN ASSOCIATION WITH DAR MAZEN AL-SANE ENGEERING CONSULTANT, KUWAIT MAIN CONTRACTOR: COMBINED GROUP CONTRACTING CO.
 SUB-CONTRACTOR : KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/03/2017
 
 | 
              
    |     PJ - 288CLIENT: MINISTRY OF ELECTRICITY & WATER - STATE OF KUWAIT - POWER STATION AND DISTILLATION PLANT PROJECTS KUWAIT  
 PROJECT NAME: DOHA SWRO DESALINATION PLANT WITH RE-CARBONATION SYSTEM (STAGE-1) MAIN CONTRACTOR : DOOSAN CO.
 CIVIL CONTRACTOR : GULF DREDING CO.
 SUB-CONTRACTOR : KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/02/2017
 
 | 
              
    |     PJ - 296CLIENT: YACOOB AL NAFISI  
 PROJECT NAME: AL NAFISI TOWER AT AL QIBLAH CONSULTANT: OHA ENGINEERING CONSULTANT
 MAIN CONTRACTOR: AL BAHAR CONSTRUCTION AND TRADING COMPANY
 SUB-CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/07/2017
 
 | 
              
    |   PJ - 306CLIENT: YUSUF AHMED ALGHANIM & SONS CO.  
 PROJECT NAME: NEW FORD SHOWROOM - TENSION PILING WORKS CONSULTANT: GULF CONSULT
 SUB-CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/03/2018
 
 | 
              
    |     PJ - 307CLIENT: STATE OF KUWAIT PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION  
 PROJECT NAME: CONSTRUCTION COMPLETION AND MAINTENANCE OF ROAD AND INTERCHANGES ON THE EXISTING 6TH RING ROAD TO INTERCHANGE 82 CONSULTANT: HALCROW GROUP Ltd IN ASSOCIATION WITH KUWAIT TECHNICAL CONSULTING BUREAU
 MAIN CONTRACTOR: METALLURGICAL CORPORATION OF CHINA LTD.
 SUB-CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/02/
 
 | 
              
    |   PJ - 310CLIENT: AJIAL REAL ESTATE AND ENTERTAINMENT CO.  
 PROJECT NAME: AL ANDALUS USE DEVELOPMENT CONSULTANT: SSH
 SUB-CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/07/2018
 
 | 
              
    |   PJ - 312CLIENT: FAHD GHASHAM AL BASSMAN  
 PROJECT NAME: CONSTRUCTION, COMPLETION & MAINTENANCE FOR AL BASSMAN TOWER - PILING WORK MAIN CONTRACTOR: UNITED EMIRATES COMPANY FOR GNERAL TRADING & CONTRACTNG CO.
 SUB-CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/11/2018
 
 | 
              
    |   PJ - 313CLIENT: NASER AL SAYER - TOYOTA  
 PROJECT NAME: AL SAYER CAR SHOWRROM CONSULTANT: AL FAROOQI ENGINEERING
 MAIN CONTRACTOR: AL BAHAR CONSTRUCTION FOR TRADING & CONTRACTING CO.
 SUB-CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 STARTED ON: 01/01/2019
 
 | 
              
    |     PJ - 314CLIENT: STATE OF KUWAIT PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION  
 PROJECT NAME: CAIRO STREET RA/200MAIN CONTRACTOR: UNITED GULF CONSTRUCTION COMPANY (UGCC)
 SUB-CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO KSCC
 SCOPE OF WORKS : PILING WORKS AND EXCAVATION SUPPORT SYSTEM FOR CAIRO STREET - CONTRACT RA/200
 
 | 
              
    |     PJ - 315CLIENT: AWTAD REAL ESTATE CO  
 PROJECT - AWTAD TOWERSMAIN CONTRACTOR - KUWAIT CONTRACTORS CO
 SUB CONTRACTOR - KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO (KSCC)
 SCOPE OF WORKS - PILING WORKS FOR COMMERCIAL TOWER AT QIBLA, PLOT 1, BLOCK 4A
 
 | 
              
    |     PJ - 316CLIENT: KUWAIT OIL COMPANY (KSC)  
 PROJECT : CONSTRUCTION OF 132 KV OHL PILE FOUNDATION FOR THREE NEW SUBSTATIONS AND ITS RELATED OVER HEAD POWER LINES IN SEKMAIN CONTRACTOR - LARSEN & TOUBRO LIMITED
 SUB CONTRACTOR - KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO (KSCC)
 SCOPE OF WORKS - PILING WORKS FOR 132 KV OVER HEAD POWER LINE
 
 | 
              
    |     PJ - 317CLIENT: PUBLIC AUTHORITY FOR HOUSING WELFARE  
 PROJECT - SOUTH AL MUTLAA HOUSING PROJECT - COMPLETION AND MAINTENANCE OF MAIN ROAD WORKS AND THEIR OWN NETWORKS OF INFRASTRUCTURE SERVICESMAIN CONTRACTOR - KOLIN INSAAT TURIZM SANAYI VE TICARET A.S
 SUB CONTRACTOR - KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO KSCC
 SCOPE OF WORKS - PILE FOUNDATION FOR HIGH VOLTAGE ELECTRICAL TOWERS
 
 | 
              
    |     PJ - 318CLIENT: THE SCIENTIFIC CENTER OF KUWAIT TSCK  
 PROJECT - THE SCIENTIFIC CENTER OF KUWAIT EXPANSION PROGRAM - BUILDING AND EXTERNAL WORKS AND MARINE WORKSMAIN CONTRACTOR - GULF DREDGING & GENERAL CONTRACTING CO KSCC
 SUB CONTRACTOR - KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO KSCC
 SCOPE OF WORKS - DESIGN, SUPPLY, INSTALLATION, MAINTENANCE OF SHORING USING SECANT PILES AND ALL ASSOCIATED WORKS
 
 | 
              
    |     PJ - 320CLIENT: INJAZAT REAL ESTATE CO  
 PROJECT - INJAZAT COMMERCIAL TOWER, SHARQCLIENT - INJAZAT REAL ESTATE CO
 MAIN CONTRACTOR - FIRST GROUP FOR GENERAL TRADING & CONTRACTING CO
 SUB CONTRACTOR - KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO KSCC
 SCOPE OF WORKS - DEWATERING, SHORING AND PILING WORKS FOR CONSTUCTION OF INJAZAT COMMERCIAL TOWER AT SHARQ, BLOCK 5, PLOT 23
 
 | 
              
    |     PJ - 323CLIENT: BOUBYAN NATIONAL REAL ESTATE SERVICES CO  
 PROJECT NAME: EXCAVATION, SHORING AND DEWATERING WORKS FOR BOUBYAN BANK NEW HEAD QUARTERSCLIENT : BOUBYAN NATIONAL REAL ESTATE SERVICES CO
 CONSULTANT: PROJACS / SSH
 CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 
 | 
              
    |     PJ - 324CLIENT: SHEIKH SALEM HAMOUD AL SALEM AL SABAH  
 PROJECT NAME: CONSTRUCTION, COMPLETION AND MAINTENANCE OF HESSAH AL MUBARAK TOWERS - PLOT 52CLIENT : SHEIKH SALEM HAMOUD AL SALEM AL SABAH
 CONSULTANT: PACE
 MAIN CONTRACTOR - FIRST GROUP FOR GENERAL TRADING & CONTRACTING CO
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 325CLIENT: SHEIKH SALEM HAMOUD AL SALEM AL SABAH  
 PROJECT NAME: CONSTRUCTION, COMPLETION AND MAINTENANCE OF HESSAH AL MUBARAK TOWERS - PLOT 161CLIENT : SHEIKH SALEM HAMOUD AL SALEM AL SABAH
 CONSULTANT: PACE
 MAIN CONTRACTOR - FIRST GROUP FOR GENERAL TRADING & CONTRACTING CO
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 326CLIENT: MINISTRY OF PUBLIC WORKS  
 PROJECT NAME: PILING WORKS FOR GANTRY SIGNS - RA/259CLIENT : MINISTRY OF PUBLIC WORKS
 MAIN CONTRACTOR - UNITED GULF CONSTRUCTION CO.
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 327CLIENT: MENA HOMES REAL ESTATE CO KSCC  
 PROJECT NAME: PILING WORKS FOR BEYOUT HESSAH PLOTS 158 & 159EMPLOYER : MENA HOMES REAL ESTATE CO KSCC
 EMPLOYERS REP - UNITED REAL ESTATE CO.
 THE ENGINEER : DAR SSH INTERNATIONAL ENGINEERING CONSULTANTS WLL
 MAIN CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 328CLIENT: MINISTRY OF PUBLIC WORKS  
 PROJECT NAME: CONSTRUCTION OF BORED PILES FOR GANTRY SIGNS - RA/259CLIENT : MINISTRY OF PUBLIC WORKS
 MAIN CONTRACTOR - METALLURGICAL CORPORATION OF CHINA
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 330CLIENT: PUBLIC AUTHORITY FOR HOUSING WELFARE  
 PROJECT : DRILLING WORKS FOR GRAVEL / STONE AGGREGATE FILLED COLUMNS OF INFILTRATION TANKS FOR SOUTH AL MUTLAA HOUSING PROJECT, CONSTRUCTION, COMPLETION AND MAINTENANCE OF THE MAIN ROAD WORKS AND INFRASTRUCTURECLIENT : PUBLIC AUTHORITY FOR HOUSING WELFARE
 MAIN CONTRACTOR - KOLIN INSAAT TURIZM SANAYI VE TICARET A.S
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 331CLIENT: PUBLIC AUTHORITY FOR HOUSING WELFARE  
 PROJECT : DRILLING AND INSTALLATION OF GRAVEL / STONE FILLED DRAINAGE COLUMNS - REF CCGC-SAM-ENG-161 [ 2020]CLIENT : PUBLIC AUTHORITY FOR HOUSING WELFARE
 MAIN CONTRACTOR - CHINA GEZHOUBA GROUP CO. LTD
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 332CLIENT: NEW VISION GLOBAL CONTRACTING CO.  
 PROJECT : PILING WORKS FOR DEEP FOUNDATION AT SHUAIBA PORTFIRST PARTY - NEW VISION GLOBAL CONTRACTING CO.
 SECOND PARTY: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 333CLIENT: STRUCTURAL ENGINEERING CO.  
 PROJECT : SHORING AND DEWATERING FOR VILLA AT SHUWAIKH RESIDENTIAL AREA, BLOCK 1, STREET 12 & 13, BUILDING 79CLIENT : PRIVATE VILLA AT SHUWAIKH
 MAIN CONTRACTOR - STRUCTURAL ENGINEERING CO.
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 335CLIENT: PUBLIC AUTHORITY FOR HOUSING WELFARE  
 PROJECT : DRILLING AND INSTALLATION OF GRAVEL / STONE FILLED DRAINAGE COLUMNS - REF CCGC-SAM-ENG-168 [ 2021]CLIENT : PUBLIC AUTHORITY FOR HOUSING WELFARE
 MAIN CONTRACTOR - CHINA GEZHOUBA GROUP CO. LTD
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 336CLIENT: PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION (MPW)  
 PROJECT : RA/265 CONSTRUCTION, COMPLETION AND MAINTENANCE OF ALGHOUS STREET FROM 7TH RING ROAD TO FAHAHEEL - AHMADI ROAD # 212CLIENT : PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION (MPW)
 MAIN CONTRACTOR - KUWAIT ARAB CONTRACTORS
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 339CLIENT: PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION (MPW)  
 PROJECT : SE/171 - PILING WORKS FOR UMM AL HAYMAN WASTE WATER PROJECT AT UMM AL HAYMANCLIENT : PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION (MPW)
 MAIN CONTRACTOR - CANAR TRADING & CONTRACTING CO.
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 340CLIENT: PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION (MPW)  
 PROJECT : RA-257- CONSTRUCTION AND MAINTENANCE OF ROADS, BRIDGES, STORMWATER DRAINAGE, SEWER AND OTHER SERVICES FOR SECTIONS OF SOUTH SURRA AREA ROADWAYS INCLUDING SEGMENTS OF DAMASCUS STREET, FIFTH RING ROAD AND KING FAYSAL BIN ABDUL AZIZ ROAD IN THE VICINITY.CLIENT : PUBLIC AUTHORITY FOR ROADS & TRANSPORTATION (MPW)
 MAIN CONTRACTOR - CHINA FIRST HIGHWAY ENGINEERING CO. LTD
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 342CLIENT: JEERAN AL KHALEEJ REAL ESTATE CO.  
 PROJECT : PILING WORKS FOR JEERAN RESIDENTIAL TOWER, FINTASCLIENT : JEERAN AL KHALEEJ REAL ESTATE CO.
 MAIN CONTRACTOR :  UNITED GULF CONSTRUCTION CO. (UGCC)
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 345CLIENT: ALSHAYA PROPERTY DEVELOPMENT CO.  
 PROJECT : BP01 ENABLING WORKS - SHORING, DEWATERING AND EXCAVATION WORKS FOR CONSTRUCTION, COMPLETION AND MAINTENANCE OF BNIED AL GAR CLINICCONSULTANT: PAN ARAB CONSULTING ENGINEERS (PACE)
 MAIN CONTRACTOR : KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO (KSCC)
 CLIENT : ALSHAYA PROPERTY DEVELOPMENT CO.
 
 | 
              
    |     PJ - 347CLIENT: ELAJ MEDICAL SERVICES  
 PROJECT : SHORING WORKS WITH SECANT PILES FOR CONSTRUCTION, COMPLETION AND MAINTENANCE OF TAIBA HOSPITAL AT SABAH AL SALEM KUWAITCLIENT : ELAJ MEDICAL SERVICES
 CONSULTANT : GULF CONSULT
 MAIN CONTRACTOR :  BACK COMBINED GENERAL TRADING & CONTRACTING CO.
 SUB CONTRACTOR: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 351CLIENT: MINISTRY OF ELECTRICITY & WATER  
 PROJECT : 400 KV DT TOWER AND GANTRY TOWER FOUNDATION WORKSCLIENT : MINISTRY OF ELECTRICITY & WATER
 SUB CONTRACTOR :  IMCO ENGINEERING AND CONSTRUCTION WLL
 SUB CONTRACTOR FOR PILING WORKS: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 354CLIENT: MINISTRY OF ELECTRICITY & WATER  
 PROJECT : SUPPLY AND INSTALLATION OF 400KV OHL FOR MAIN SUBSTATION BOUBYAN (Z)CLIENT : MINISTRY OF ELECTRICITY & WATER
 MAIN CONTRACTOR :  ELSEWEDY ELECTRIC FOR TRANSMISSION AND DISTRIBUTION OF ENERGY S.A.E
 SUB CONTRACTOR FOR PILING WORKS: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO.
 
 | 
              
    |     PJ - 356CLIENT: AFRA RESIDENTIAL TOWER – KUWAIT CITY  
 PROJECT : AFRA RESIDENTIAL TOWER – KUWAIT CITYCONSULTANT : DAR MIMAR CONSULTANTS
 MAIN CONTRACTOR :  ALGHAZI SAND KHATTAB COMPANY
 SUB CONTRACTOR FOR PILING WORKS: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO. (KSCC)
 
 | 
              
    |     PJ - 357CLIENT: MOHAMED NASER AL SAYER & SONS EST. CO. WLL  
 PROJECT : PILING, SHORING & DEWATERING WORKS FOR CONSTRUCTION, COMPLETION AND MAINTENANCE OF GARAGE, CAR SERVICE AND MAINTENANCE CENTER AT SHUWAIKH FOR AL SAYER (BID PACK -01 ENABLING WORKS)CLIENT : MOHAMED NASER AL SAYER & SONS EST. CO. WLL
 CONSULTANT : NEZAR AL-ANJARI CONSULTING BUREAU
 MAIN CONTRACTOR :  KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO (KSCC)
 
 | 
              
    |     PJ - 358CLIENT: AL SEEF TOWER – ARABIAN GULF STREET - KUWAIT  
 PROJECT : PILING WORKS FOR AL SEEF TOWER – ARABIAN GULF STREET - KUWAIT CONSULTANT : JASEM AL-SHEHAB CONSULTANTS
 MAIN CONTRACTOR :  FIRST UNITED BUILDING CONSTRUCTION CO  (FUBC)
 SUB CONTRACTOR FOR PILING WORKS: KUWAIT BRUCKNER CONSTRUCTION CONTRACTING CO. (KSCC)
 
 | 
       
    
 |   PJ-190Main Contractor - Kuwait Bruckner Const Cont Co (KSCC)JAHRA ROAD
 
 | 
  
   |   PJ-193Main Contractor - Kuwait Bruckner Const Cont Co (KSCC)KCC
 
 | 
  
   |   PJ-195Main Contractor - Alghanim InternationalALGHANIM INTERNATIONAL AL ZOUR
 
 | 
   |   PJ-196Main Contractor - Kuwait Bruckner Const Cont Co (KSCC)WAFRA MALL
 
 | 
  
   |   PJ-198Main Contractor - Gulf SpicBUKHAMSEEN INTERNATIONAL INCINERATOR STACKS AT TGTU UNIT 24 - MAB
 
 | 
    
  |   PJ-205Main Contractor - GS Engineering & ConstructionGS ENGINEERING & CONSTRUCTION PILE COMPRESSION TESTS AT TANK FARM
 
 | 
  
     |   PJ-206Main Contractor - KEC International LimitedCONSTRUCTION OF PILE FOUNDATIONS ON 400KV OHTL STARTING FROM EXISTING LINES NEAR NUWAISEEB AND CONNECTING TO PROPOSED SUBSTATIONS IN SABAH AL AHMED CITY
 
 | 
  
    |   PJ-207Main Contractor - KEO ConsultantsAL SHAYA PROPERTY DEVELOPMENT CO. CONSTRUCTION OF BORED PILES DIA 1500MM FOR BURJ AL SHAYA
 
 | 
    |   PJ-208Main Contractor - Technimont Co.TECHNIMONT CO. NEW AGRP/AGRP REVAMP PROJECT “NARGP” AT MAA REFINERY
 
 | 
    |   PJ-209Main Contractor - Kuwait Bruckner Construction Cont. CoABDUL HUSSAIN BAHMAN CO. PILING WORKS FOR BAHMAN TOWER – AL SHAAB
 
 | 
    |   PJ-210Main Contractor - Burhan International Construction CoCONSTRUCTION , COMPLETION AND MAINTENANCE OF INTERCHANGES ON MAIN HIGHWAYS – 6TH& 7TH RING ROAD MOTORWAYS CONNECTING TO NEW HOUSING AREA AT WEST JLEEB AL SHUYOUKH – CONSTRUCTION OF REINFORCED CONCRETE PILES AT VARIOUS LOCATIONS.
 
 | 
    |   PJ-212Main Contractor - FIRST UNITED GENERAL TRADING& CONTRACTING CO.KUWAIT INVESTMENT AUTHORITY – SHORING,
DEWATERING AND PILING WORKS.
 
 | 
    |   PJ-215Main Contractor - Kuwait Bruckner Construction Cont. Co.CONSTRUCTION OF NEW 132KV OHL TO THE NEW SUG-B SUBSTATION AT SUG.
 
 | 
    |   PJ-216Main Contractor - Kuwait Bruckner Construction Cont. Co.CONSTRUCTION, COMMISSIONING, HANDING OVER MAINTENANCE OF MEP OFFICE EXTENSIONS FOR WORKSTATIONS.
 
 | 
    |   PJ-217Main Contractor - Bayan National Trading & Contracting Co.PILE TESTING & CONSTRUCTION OF PILES DIA 700 / 900MM FOR CONSTRUCTION & MAINTENANCE FOR
STADIUM & SPORTS FACILITY
 
 | 
    |   PJ-220Main Contractor - Kuwaiti Manager Company for Managing Real Estate ProjectsKUWAIT NATIONAL GUARD HEADQUARTERS
TENSILE TENTS.
 
 | 
 
 
    |   PJ-222Main Contractor - Hyundai Heavy IndustriesAZ-ZOUR NORTH PHASE I- INDEPENDENT WATER & POWER PLANT SECANT PILE WALL + DEWATERING
 
 | 
 
    |   PJ-227Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)THE AVENUES PHASE IV EXCAVATION, DEWATERING & SHORING
 
 | 
  
  
    |   PJ-229Main Contractor - Sadeem Al KuwaitAL TAYEB COMPLEX - PILING
 
 | 
  
  
    |   PJ-232Main Contractor - Alghanim International General Trading & Contracting Co.AL FARWANIYA COURT COMPLEX - SHORING & DEWATERING
 
 | 
  
  
    |   PJ-233Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)SABAH AL AHMED SEA CITY - RD 285 BRIDGES – PILING
 
 | 
  
  
    |   PJ-234Main Contractor - KEC International400KV GANTRY WORKS - AL ZOUR SUBSTATION - PILING
 
 | 
  
  
    |   PJ-235Main Contractor - First United Co.HONDA CAR SHOWROOM - PILING WORKS
 
 | 
  
    
    |   PJ-238Main Contractor - Structural Engineering Co.OXYGEN HEALTH CLUB- SHORING, DEWATERING & PILING
 
 | 
  
    
    |   PJ-239Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)EXCAVATION, DEWATERING & PILING WORKS - MARKAZ TOWER
 
 | 
    
    |   PJ-240Main Contractor - Kuwait Building HouseHAWALLY COURT COMPLEX
 
 | 
  
      
    |   PJ-242Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)CONSTRUCTION OF THREE STEEL CEMENT SILOS 500 TONS AT SHUWAIKH PORT (NEAR BERTH NO. 8)
 
 | 
  
   
   
    |   PJ-244Main Contractor - Combined Group Contracting Co.DESIGN DEVELOPMENT, REHABILITATION AND MAINTENANCE FOR AL-SALAM PALACE-SECANT PILES
 
 | 
   
   
    |   PJ-246Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)THE AVENUES PHASE IV B- EXCAVATION, DEWATERING & SHORING
 
 | 
   
    |   PJ-248Main Contractor - Option One InternationalWARBA ISLAND RESIDENTIAL TOWER- BP2- PILING
 
 | 
   
    |   PJ-249Main Contractor - Petrofac International/ Samsung Engineering/ CB & I NederlandJI 2025-MAB1- CLEAN FUEL PROJECT - PILING
 
 | 
    |   PJ-251Main Contractor - Daelim Co.KNPC SULPHUR HANDLINGFACILITIES - SHORING AND DEWATERING WORKS
 
 | 
   
      
    |   PJ-252Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)SABAH AL AHMAD SEA CITY PROJECT , PHASE A4- PUMPING STATION – SECANT PILING WORKS
 
 | 
 
  
    |   PJ-253Main Contractor - Daelim Co.KNPC SULPHUR HANDLINGFACILITIES - PILING WORKS
 
 | 
  
  
   
    |   PJ-254Main Contractor - Canar Trading & Contracting Co.RA/248 - DESIGN & BUILD OF TEMPORARY ELEVATED U-TURNS ALONG NUWASEEB ROAD- PILING
 
 | 
 
 
  
    |   PJ-257Main Contractor -MA Kharafi & SonsTENSION AND SECANT PILES FOR JAHRA HOSPITAL
 
 | 
 
  
   
    |   PJ-259Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)PILING WORKS FOR BABEL RESTAURANT - MARINA
 
 | 
  
  
  
  
  
   
    |   PJ-260Main Contractor - Bayan National Trading CompanyWORKS FOR INFECTIOUS DISEASE HOSPITAL
 
 | 
  
  
   
    |   PJ-261Main Contractor -First Group CompanySHORING, DEWATERING AND PILING WORKS FOR AL KHALED TOWER, SALMIYA
 
 | 
  
  
   
    |   PJ-262Main Contractor - Bader Al Mulla & BrosPILING WORKS FOR MEW # 62 - AZZOUR & ABDALY
 
 | 
 
 
     
   
    |   PJ-264Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)PILING SHORING & DEWATERING WORKS FOR CENTRAL BODY SHOP - SHUWAIKH
 
 | 
  
     
   
    |   PJ-265Main Contractor - Bayan National Trading CompanyPILING WORK FOR INFECTIOUS DISEASE HOSPITAL
 
 | 
  
  
  
      
   
    |   PJ-266Main Contractor -Kuwait Building CompanySHORING, DEWATERING AND PILING WORKS FOR AL KHANA RESTAURANT - ABU HALIFA
 
 | 
  
  
  
   
    |   PJ-268Main Contractor -Nasa ConstructionPILING WORKS FOR TAMDEEN SQUARE, SABAH AL SALEM
 
 | 
 
    
   
    |   PJ-275Main Contractor - Kalpataru Power Transmission LTD SUPPLY AND INSTALLATION OF HIGH VOLTAGE OHTL IN KUWAIT. MEW/25/2013-2014
 
 | 
  
  
    
   
    |   PJ-279Main Contractor -Combined Group CoNEW EASTERN CAR PARK IN MINISTRIES COMPLEX BUILDING
 
 | 
  
  
    
   
    |   PJ-291Main Contractor - Kuwait Bruckner Construction Contracting Co. (KSCC)SEPCO III - PILING WORKS DIA 600 AT AZ ZOUR SOUTH, CCGT-3 PROJECT
 
 | 
  
  
    
   
    |   PJ-293Main Contractor - First United Building Construction & Decorations Co.SHORING AND DEWATERING WORKS FOR FAWAZ AL MARZOUK VILLA, SHUWAIKH
 
 | 
  
     
   
    |   PJ-294Main Contractor - Al Argan General Trading & Contracting Co.SHORING, DEWATERING & UPLIFT PILING WORKS FOR HYUNDAI EXT GARAGE & OFFICES AT SHUWAIKH
 
 | 
   
    
   
    |   PJ-295Main Contractor -KCPCCONSTRUCTION, COMPLETION AND MAINTENANCE OF BRIDGE AND OTHER SERVICES AT GULF STREET ON AL BIDDA ROUND ABOUT
 
 | 
  
  
   
    |   PJ-304Main Contractor - SEPCOIIISHORING & DEWATERING WORKS - AZZOUR, KUWAIT
 
 | 
  
  
     
    |   PJ-305Main Contractor - United Gulf Construction Co - UGCCBORED PILES FOR RA/259 AT SALMI ROAD
 
 |